Press - News
Archive
Press - News
Archive
Press - News
Archive

Pressure test of a boiler in Roosendaal, the Netherlands

On May 25th, 2010 took place the positive hydrostatic pressure test of the boiler on technological line No 1 in Roosendaal, the Netherlands. The contract contains the assembly of two technological lines in municipal waste incineration plant.

 

The Construction Manager is Mr. Józef Dąbrowski. The hydrostatic pressure test of the boiler on technological line No 2 is planned on June 9th, 2010, this realization is planned to be finished on September, 2010.