The onset of October saw the start of the installation of a BFB biomass powered system at the CHP plant in Jönköping, Sweden. Mostostal is responsible for installing the system together with channels, equipment and low pressure pipelines. The schedule foresees: pressure test - 09.04.2014, completion of works - end of April 2014.