The completion of the modernisation of the processing line in the sugar factory "Strzyzow" S.A.
Contract with Meat Processing Plant "Konskowola" S.A. for construction of a production hall in GW system. Time for completion - 05.2004 to 10.2004.
Assembly of the ducts and piping of the boiler in Shoghall, Sweden.
Time for completion: 06.2004 to 04.2005.
Manufacture, delivery, assembly and anticorrosive protection of the bridge steel construction on the Gwda river in Dobrzyca. Time for completion: 07.2004 to 09.2004.
Cycling race for the Cup of the President of Pulawy. The cyclists from the Folk Sports Club "Pogon Mostostal Pulawy" sponsored by our company took place in this race, obtaining good notes.
The completion of the assembly of a power boiler in the paper plant Borlänge in Sweden.
Contract with Austrian Energy & Environment in Gratz for manufacture of approx. 600 t support structure for 2 technological lines in an incineration plant MVA Lausanne /Switzerland. Time for completion - 05.2004 to 12.2004.
Modernisation of the product house in the sugar factory "Strzyzow" S.A.
Time for completion: 05.2004 to 06.2004.
Disassembly of the old electrofilter and assembly of the new one in the power plant Siekierki in Warsaw. Time for completion: 05.2004 to 06.2004.
Erection of the sorting plant in Pruszkow. Time for completion: 06.2004 to 09.2004.