2004
Assembly of the steam and water system piping in Vattenfall Värme Uppsala AB, Sweden.
Delivery and assembly of the dedusting installation for 2 arc furnaces in the steel plant BES Brandenburg, Germany. Time for completion: 05.2004 to 08.2004.
The completion of the assembly of the electrofilter in the paper plant Borlänge in Sweden.
Completion of works for the main part of the contract for building Melamine Plant III in Nitrogen Works "Pulawy".
Completion of manufacture and assembly of 270t steel structure for an electro-filter. The investor was Alstom Finland.
Completion of rebuilding of a railway platform area with an umbrella roof at the Pulawy-Miasto railway station. The steel structure made was 85t for the umbrella roof together with the casing. The passenger shelter structure was cladded with aluminium panels and the arc structure of the roof was made with transparent polycarbonate with a heated ystem of drainage.
Contract with Voest-Alpine Linz, Austria for steel structure for stainless steel foundry Carinox in Belgium. Time of completion - 04.2004.
Modernization works on the bridge over the Vistula River near Kiezmark.
Contract with Galvatek Ltd Warsaw for completing a galvanizing line for PZL Okecie Warsaw. Scope of works: 25 galvanizing chambers made of acid-proof materials partly lined with chemoresistant fabrics. Measures of a chamber: 1205x1950x6100. Time of completion - 04.2004.
Assembly of a hall for the Lublin International Fair.